CDM 2015: What are the changes and how might they affect you?

  • 27 Apr 2015

Construction (Design and Management) Regulations 2015

Construction (Design and Management) Regulations 2015

The Construction (Design and Management) Regulations 2015 came into force earlier this month, bringing a series of changes to the way in which construction clients, consultants and contractors conduct health and safety procedures across the construction industry.

Under the new legislation, clients both domestic and commercial will have greater responsibility for overseeing health and safety management procedures and how these are conducted by the people they employ. Should a client fail to adhere to the expected standards, they face increased liability and risk of legal action.

CDM 2015 replaces the previous 2007 version and is intended to make it easier for domestic and commercial construction clients to manage individual health and safety standards. To ensure they meet the latest requirements, construction clients must adhere to the following laws in order to meet the new health and safety standards:

  • Assemble a competent professional team and ensure that the roles of team members are clear
  • Ensure sufficient time and resources are allocated at appropriate stages of the project to adequately and appropriately deal with health and safety issues
  • Ensure that there are effective mechanisms in place for project team communication and that they work.
  • Provide suitable welfare facilities for the duration of the construction work

Clients must appoint a principal designer

The new legislation also states that clients must appoint a principal designer, whose responsibilities will include planning and managing the pre-construction phase, and co-ordinating on-going health and safety procedures. Given the demands of the latest legislation, existing CDM co-ordinators may no longer be suitable for the role, and firms must ensure they handle the shift from CDM co-ordinator to principal designer correctly.

Almost everyone involved in a construction project will be affected by CDM 2015, though the legislation does recognise that the client is the person best placed to monitor standards throughout. Other duty holders with legal obligations under the new legislation include the principal designer, principal contractor and construction workers. It is the responsibility of the client to ensure all the above parties are skilled professionals capable of safeguarding and upholding the relevant health and safety procedures in line with the new CDM regulations.

CDM 2015 designed to simplify health and safety

Charles Brien, construction lawyer at HBJ Gateley: While the new legislation is designed to simplify health and safety requirements, the onus is now on clients to understand the subtle shift in liability and to change their policies and practices accordingly.

Firms with a poor or substandard health and safety record will be closely monitored during the transition to ensure they are putting plans in place to meet the standards set by the latest CDM regulations.

Construction clients must appoint a professional team or contractor to manage health and safety practices and provide sufficient resources and safety equipment to ensure that work can be undertaken safely on site. Health and safety suppliers can provide firms with the appropriate safety equipment required to complete their construction project safely and in accordance with the new CDM legislation.

Making working practices safer

A spokesperson from Manchester Safety Services: Any revision of the health and safety standards which makes working practices safer is a positive step. Its important that construction clients understand the changes and take appropriate measures.

Health and safety bosses have proposed that all projects started before the 6th April will have until 6th October to appoint a principal designer, whilst all new projects must adhere to the CDM 2015 legislation from the outset.

.

Manchester Safety Services Ltd is a leading distributor in Road Safety Equipment, Contractors Tools and Site Equipment and Personal Protective Equipment.

Leave a Reply

Latest news

Abloy
Renderplas

Renderplas shadow gap beads throw shade

For architects and designers looking to avoid traditional skirting boards, architraves and cornices, Renderplas offers its range of PVC plasterboard shadow gap beads for dry lining systems.

Posted in Articles, Building Industry News, Building Products & Structures, Floors, Interior Design & Construction, Interiors, Posts, Render, Restoration & Refurbishment, Retrofit & Renovation, Walls

MCRMA

First MCRMA members’ roadshow takes place at Siderise

Members of the MCRMA, the trade association for the metal cladding and roofing industry, had an exclusive opportunity to explore and discuss the changes affecting the construction sector at the first of the association’s roadshow events hosted by Siderise at its HQ and manufacturing facility in South Wales.

Posted in Articles, Building Associations & Institutes, Building Industry Events, Building Industry News, Building Products & Structures, Building Regulations & Accreditations, Building Services, Cladding, Exhibitions and Conferences, Health & Safety, Restoration & Refurbishment, Retrofit & Renovation, Seminars, Walls

BMBI