Visit the Brett Martin Daylight Systems web site

Bachy Soletanche digs deep at pipeline

A Bachy Soletanche product story
Edited by the Buildingtalk editorial team Sep 3, 2007

Leading geotechnical specialist, Bachy Soletanche has recently completed work on a circular secant shaft near Ammanford, South Wales.

The shaft will assist in the construction works of the Felindre to Tirley natural gas pipeline, transporting natural gas from Tirley to the two new terminals under construction at Milford Haven in Pembrokeshire.

Barhale Construction plc awarded BSL the circular shaft contract on the 90kilometre stretch from Felindre to Brecon.

However, the essential pipeline works - in its entirety - will run from Felindre to Tirley, covering a total of 196kilometres.

The two sections are to be built by two separate contractors.

National Grid has estimated that more than 20 percent of UK gas requirements will run through the natural gas pipeline, helping to meet the UK's growing demands and address the decline in North Sea reserves*.

The shaft is vital in the preparation works for the project, as a tunnel-boring machine (TBM) will be lowered 22metres below ground to begin the tunnelling works for a section of the pipeline.

Steve Mallinson, contract manager for Bachy Soletanche commented: "BSL designed the shaft around the ground conditions and the required depth.

Our design was for a hard/hard secant circular shaft using large diameter auger (LDA) piles".

"The original design was for a traditional Caisson Shaft, but due to large boulders found in the ground we came up with a piled solution as an alternative." The hard/hard secant piling method requires the use of reinforced concrete piles for permanent retention.

Secant walls are constructed in two stages with the primary, female piles installed first.

Secondary, male piles are then cut into the primary piles.

BSL's design was to create a circular shaft using the secant piling method that would provide a shaft large enough to accommodate the TBM.

In order to create the circular shaft, 32 rotary piles of 1200mm diameters are bored to a depth of 24metres.

The piles are bored through a ground profile including one metre of soft clay, dense gravel with large boulders to 15.5 metres, and weak to strong mudstone down to 25metres.

A Bauer BG 24 was utilised as the ground conditions required heavy- duty drilling equipment.

However, even this powerful rig still required additional torque, and a torque multiplier was employed to increase the rig's torque from 24Tm to 48Tm.

Steve Mallinson continued: "Our rig needed enough power to drill through the large boulders and screw the casing down to 24.0m" The piles are reinforced with steel, yet carbon fibre bars are used for piles in the area of the tunnel drive.

This creates a "soft eye" at the start of the tunnel - allowing the tunnelling to begin with ease".

Bachy Soletanche began work on site in late March and completed the project at the end of May.

Further works on the project will continue throughout the year.

Not what you're looking for? Search the site.

Back to top Back to top

Contact Bachy Soletanche

Related Stories

Contact Bachy Soletanche
Newsletter sign up

Request your free weekly copy of the Buildingtalk email newsletter ...

Visit the Brett Martin Daylight Systems web site

Search by company

A Pro-talk Publication

A Pro-talk publication