Bachy Soletanche adds levels to
Birmingham Cube
Leading geotechnical specialist, Bachy Soletanche Limited has recently completed piling works at the site of a planned iconic building, The Cube in Birmingham.
The Cube will be the sister building of the Mailbox and is set to be a major new mixed use development including up-market apartments, retail outlets and the first roof-top restaurant to overlook the city The Cube has been designed by Ken Shuttleworth - one of the architects to contribute to the creation of the Gherkin in London - and is receiving a lot of interest with many of the apartments already sold
This article was originally published on Buildingtalk on 5 Feb 2007 at 8.00am (UK)
Related stories
Bachy Soletanche piling solution at heritage site
Bachy Soletanche has provided an innovative piling solution at Liverpool's Half Tide Dock,
Bachy Soletanche at Chancery Place project
Bachy Soletanche set to complete a 'high' profile project at Chancery Place in Manchester.
Once complete, the building will include 17 storeys and a five floor basement which has been designed to make the best use out of the premium 60metres by 70metres space.
Bachy Soletanche Limited (BSL) was awarded the GBP1.7million piling works contract by BuildAbility to design and deliver a retaining wall.
Working closely with the developers from an early stage in the project, a contiguous piled retaining wall was chosen to be installed around the perimeter of the site.
Further reading
Bachy Soletanche piling at Crossharbour site
Bachy Soletanche Limited has recently completed its first stage of piling works at Crossharbour, the high-profile development based in London City centre.
Piling work for Carlow project in Ireland
Bachy Soletanche has completed piling work for a euro15million Waterfront office development at the heart of Carlow - one of Ireland's fastest growing towns.
Bachy Soletanche constructs slurry cut-off wall
Bachy Soletanch has just completed a project for Urban Regen to carry out the construction of a slurry cut-off wall as part of preparation works for a new residential development.
Steve Mallinson, contracts manager for Bachy Soletanche commented: "We had many issues to consider in the design process due to the sites city centre location by the canal, its limited space and the buildings adjacent to the east and west sides of the site".
"We worked closely with the project team to provide a solution which satisfied all parties".
Using the large diameter auger (LDA) piling technique, BSL installed 226, 900mm diameter piles at 1050mm spacings.
These were drilled up to a depth of 24metres.
In order to carry out the process successfully, BSL skipped three piles - after installing the first pile - to avoid concrete flowing into the next borehole and therefore damaging the original pile.
However, when piling works commenced, BSL came across an unexpected problem of groundwater as Steve continued: "We encountered up to 6metres of groundwater when boring out the 24 metre piles".
"As a result, we had to re-evaluate our methods of pouring the concrete into the bored pile".
This required the use of a Tremie pipe which was put inside the reinforcement cage down to the toe of the pile.
Concrete was then poured through the pipe and gradually lifted out as the concrete filled the pile".
"By filling the borehole from the base up, the groundwater is displaced to the top of the cast concrete." Steve added.
Included in the design is a car lift in the southwest corner of the site.
With space being at a premium, BSL replaced the LDA piles in this area with 24Nr, 273mm diameter minipiles bored to a depth of 24 metres.
Another 54 minipiles were used to the west of the site alongside the LDA piles which were drilled to a depth of 12metres in order to add further support to the adjacent building.
Finally, BSL constructed 30 king post piles to provide foundation for a ramp which is required for future building works.
Each king post pile was formed in a 900mm diameter pile, with a 400mm square steel column concreted into the toe of the pile.
These piles run in two parallel rows down the centre of the site.
With all the initial piling works complete, the site has been excavated exposing the piles between 14metres and 19metres to create a new ground level.
BSL returned to the site after the excavation to construct 12 temporary anchors to hold back the retaining piles on the east side of the site.
BSL completed the piling project at the end of 2007.