Bachy Soletanche prepares new Canary
Wharf site
At the Riverside South site in Canary Wharf, Bachy Soletanche Limited is constructing a considerable 610m diaphragm wall for two high-rise structures.
The site is one of the last river fronted areas remaining at Canary Wharf, located on the west side of the Isle of Dogs The two buildings, proposed to be the second tallest in the Wharf, are specially designed to compliment the skyline without compromising the views of the famous three buildings - One Canada Square, HSBC Tower and Citigroup Centre - that have stood for several years
This article was originally published on Buildingtalk on 5 Feb 2007 at 8.00am (UK)
Related stories
Bachy Soletanche piling solution at heritage site
Bachy Soletanche has provided an innovative piling solution at Liverpool's Half Tide Dock,
Bachy Soletanche at Chancery Place project
Bachy Soletanche set to complete a 'high' profile project at Chancery Place in Manchester.
The leading geotechnical firm is working in a joint venture with Costain under a contract with Canary Wharf Contractors Limited.
The project includes the sophisticated diaphragm wall technique, as Ben Hardy, Bachy Soletanche Limited's Contract Manager for the Riverside project, explained: "We were awarded the ground works project to construct a basement wall around the perimeter of the site, having proposed the diaphragm wall technique in lieu of the conforming secant pile scheme".
"The superior watertightness of a diaphragm wall for the excavation of the three floor basement was a big selling point".
Further reading
Bachy Soletanche piling at Crossharbour site
Bachy Soletanche Limited has recently completed its first stage of piling works at Crossharbour, the high-profile development based in London City centre.
Piling work for Carlow project in Ireland
Bachy Soletanche has completed piling work for a euro15million Waterfront office development at the heart of Carlow - one of Ireland's fastest growing towns.
Bachy Soletanche constructs slurry cut-off wall
Bachy Soletanch has just completed a project for Urban Regen to carry out the construction of a slurry cut-off wall as part of preparation works for a new residential development.
A diaphragm wall is constructed in panels with the Riverside South project requiring a massive 96 panels to complete the 610m wall.
However before the panels can even begin to be installed, a guide wall trench is being created to maintain the accuracy of the wall construction.
The 'panels' are a combination of 1000mm and 1200mm widths, and are constructed using 2.8m long rope grabs.
They consist of three "bites" - a "virgin" bite, a "stop-end" bite and a "centre bite".
When these three bites are complete, each panel is up to 7m in length.
In order to form watertight joints between the panels, stopend casings containing a double sided water bar are placed at both ends of the first 'panel' prior to concreting.
The stopend is designed so that half of the waterbar is cast into the panel and half is protected/contained within the structure of the stopend.
These stopends are then withdrawn once the adjacent panels are excavated, and the second half of the waterbar is left behind to be encased in the concrete of the adjacent panels.
Ben Hardy continued: "In normal circumstances we would just construct the diaphragm wall, but with the site being on a large bend in the River Thames, the Riverside site has a long history of boat building and boat maintenance".
"Dry docks have been built over the top of the other for centuries before finally being crudely backfilled in the middle of the twentieth century".
"A diaphragm wall grab is not designed to go through these timber, stone, concrete and steel structures, and therefore the project involves a significant amount of rotary coring".
The old docks are cored out using 1500mm diameter coring equipment and rock augers down to a depth of 12m.
The hard cored out material is then replaced with a soft slurry mix which the grab can easily 'bite' through after it has set.
Ben Hardy concluded: "We have a systematic approach to this part of the project ensuring that the docks are fully cored out on the alignment of the panels".
"For the diaphragm wall operation to run smoothly we can't afford to have a big lumps of material obstructing the grabs".
When the wall is complete in mid-spring 2008, the ground will be excavated by Costain with staged installation of ground anchors.