Demolition services at waste water treatment plant
Dallas Contracting, recently completed dismantlement phase 1 of 2 at an industrial waste water treatment plant in Westchester County, New York.
Dallas Contracting Co (Dallas Contracting) was contracted by a general contractor to perform the selective dismantlement of equipment, piping and mezzanines in a waste water treatment plant for a large Fortune 500 client.
The work needed to be conducted in phases to allow the general contractor (GC) to shutdown the front section of the plant while maintaining the back section of the plant.
Items demolished included a denitrification tank, lime slurry tank, mechanical lift, associated pumps, valves, piping and mezzanines.
Time was of the essence so that the GC could re-install the new equipment.
In order to perform the work safely and efficiently, Dallas Contracting utilized laborers with cutting torches as well as demolition saws to carefully cut the steel and metals into small manageable pieces.
Extreme care had to be taken as the crew was working in close proximity to active electrical and process lines that needed to remain intact.
Fire resistant tarps were utilized to protect equipment and lines that were to remain.
The metal scrap pieces were then carted out of the room and into a scrap metal container.
During the demolition efforts, a fire watch was maintained (fire extinguishers were readily available) and proper ventilation was maintained.
The project was completed within a week and without incident or injury.
Not what you're looking for? Search the site.
Browse by category
- Building Industry News (7919)
- Information Technology (2961)
- Building Structures and Products (15785)
- Building Services (11320)
- Building Systems (1482)
- Security and Fire Protection (2472)
- Site Preparation (1588)
- Landscaping (563)
- Plant, Equipment and Hire (1776)
- Civil Engineering (1465)
- Interiors (1258)
- Latest Exhibitions and Awards (24)