News Release from: Enerpac | Subject: Beijing birds nest
Edited by the Buildingtalk Editorial
Team on 09 February 2007
Enerpac helps the Beijing birds nest
After successful disconnecting the 45.000 ton steel structure from its temporary support piers, Enerpac helps the Beijing's 'bird's nest. to stand on its own feet.
After two years of construction, the main venue for the 2008 Beijing Olympic Games came to a final and most important part of the construction of its steel structure: the dismantling of the temporary support towers When presenting their stadium design to the Chinese jury, the Swiss architects Herzog and Meuron used the analogy of a bird's nest
This article was originally published on Buildingtalk on 23 Jan 2003 at 8.00am (UK)
Related stories
The World's Highest Bridge
Enerpac and the Millau Viaduct, France: a great new work of French Structural Engineering and Spanish/American Hydraulic Technology.
Hydraulic System Pushes 4000 Ton Deck Into Space
The deck of what is going to be the world's highest bridge is being launched over the Tarn valley, in the South of France, with hydraulic technology from Enerpac.
Everyone loved the idea of a bird's nest and so they won.
Perhaps because of the culinary association; in China, a bird's nest is very expensive and believed to be extremely healthy, something you eat on very special occasions.
During construction, the crisscrossed interwoven steel roof construction of the bird's nest roof was supported by 78 temporary steel columns.
Further reading
Enerpac Hydraulics Lifts Entire Old Mill
Lifting an entire mill from 1699 with all its fittings by two metres is quite something. The 700 ton 'chore' was lifted in three days with Enerpac hydraulic lifting equipment.
Synchronous Lifting With Digital Hydraulics
Whether it's a bridge or whole building, with the unique Enerpac Synchronous Lifting System, lifting, lowering or positioning can be carried out completely automatically to a high degree of accuracy.
Intelligent Hydraulics Stretch Out The Prado
Spain's prestigious Prado Museum in Madrid is expanding its exposition room to 16.000 square meters.
For additional stability, the huge 'twigs' were welded onto the supports.
After completion of the bird's nets construction the 'twigs' had to be cut off the support piers, before dismantling of the piers could start.
In most western countries, cranes would have been hired to do the lifting job while welders would cut off the welds off the 78 supports laid during construction.
However, due to the extreme high cost of hiring a number of 800-ton cranes for several days in China, a smarter and less expensive solution needed to be found.
Key pre-requisites to the entire cutting-operation were safety, control, stability and cost.
Enerpac, known from many complex hydraulic applications around the globe and in the Chinese market especially for their hydraulic solutions for moving roofs (NanTong stadium) and moving structures (Shanghai concert hall) was consulted.
Basically the disconnecting and dismantling process of the temporary supports comes down to synchronically and fully controlled lifting the structure of its supports, cutting the welds, followed by controlled and synchronized stage-lowering to allow the removal of the 50mm think leveling plates that were used during construction.
Computer-controlled hydraulics is the perfect match for jobs like this, and Enerpac was granted the contract to perform the stage lifting and lowering of the roof.
The entire configuration including the central computer, satellite computer-controllers, 156 double-acting high-pressure hydraulic cylinders and 55 electronically controlled hydraulic power units was specified and custom designed by ENERPAC.
For added safety, control and accuracy, multi-functional valves, load sensors, stroke sensors, shift detection and a digital feedback system were integrated.
The design of the bird's nest is based on three construction circles; an outer circle, a central circle and an inner circle.
Each circle has a specific number of supporting piers, varying from 24 for the outer and central circles and 30 for the inner circle.
For load, control and accuracy reasons the 78 support points including their hydraulic systems are divided into 10 regions, each of which with its own satellite controller.
For the actual stage lifting and lowering process each support pier is equipped with two 150-ton double-acting cylinders.
At the central computer all load and stroke data are pre-programmed for a fully controlled lifting and lowering process.
During the stage lowering process the bird's nest is alternatively supported by the hydraulic cylinders and the leveling plates on the temporary supports.
After successful disconnecting the 45.000 ton steel structure from its temporary support piers, last year November, the bird's nest stood on its own "feet" for the first time.
Stadium key facts.
Start of construction: Dec 2003.
Roof completion - Oct 2006.
Stadium completion - End of 2007.
Gross floor area - 258.000 square meters.
Seat capacity - 80.000 (11.000 temporary seats will be added after the 2008 Olympics.
Structure - 36km of unwrapped steel length.
Height - 69,2m above pitch levels.