Technical Guidance Notes - Boundary Line
Sites
Reinforced concrete structures built against the site's boundary line can prove difficult and complex for traditional waterproofing systems.
Martin Radford, National Sales and Marketing Manager at RIW on Technical Guidance Notes - Boundary Line Sites Conceptually, waterproofing solutions should be kept as simple as possible
This article was originally published on Buildingtalk on 6 Mar 2006 at 8.00am (UK)
Related stories
Protect against water ingress and Radon emissions
Developer from Newton Abbot, Devon contacted RIW to seek advice on how best to protect a proposed development in Brixham against water ingress and Radon emissions.
Colour coded waterproofing
High performance 'Colour Coded', seamless and fully bonded waterproofing systems help eliminate the risk associated with waterproofing today's structures.
However, reinforced concrete structures built against the site's boundary line can prove difficult and complex for traditional waterproofing systems.
So how can you simplify your waterproofing strategy for today's concrete structures built on boundary lines, and what are the waterproofing strategies available to you? For many reasons such as ground conditions, land restrictions and utilisation of space, many of today's structures are built up to the boundary line generally formed using concrete or sheet piles.
These forms of construction provide little or no working space which limits your waterproofing options to the following:.
Further reading
Lift pits and waterproofing strategy
Lift pits are perhaps the most vulnerable part of a sub-structure in any building and they are often overlooked as a critical element of the waterproofing strategy.
Case Study: Wandsworth Southside Shopping Centre
RIW Limited was called in by Leslie Jones Architects to advise on the waterproofing strategy for the basement sub-structure of the GBP70m refurbishment of Wandsworth Southside Shopping Centre.
Technical seminar at Bristol Architecture Centre
RIW technical seminar at The Architecture Centre, Bristol to give guidance in identifying common problems associated with waterproofing today's structures and how to avoid them.
(i) Pre-applied waterproofing using the piled structure as the back shuttering.
(ii) Waterproofing the structure internally.
For the purpose of this article we will concentrate on pre-applied systems.
As outlined in BS 8102:1990 Code of Practice for the protection of structures against water from the ground, there are a number of important considerations that should be ascertained at this point.
- It is important to understand the client's expectations, the proposed usage of the basement and any possible change of use in the future.
- What has the site investigation told you about the geology of the site? For instance, where is the water table and how free draining is the soil?.
- Is it possible to install effective sub-soil drainage throughout the site?.
These considerations will influence the selection and design of your waterproofing strategy.
Pre-applied Waterproofing Currently, there are three generic forms of pre-applied membranes:.
- Sodium Bentonite Geo-composite membranes.
- Pressure sensitive adhesive laminates.
- Mechanically bonded plastic laminates.
Each generic system has its attributes and limitations and it is important that these are considered and fully understood prior to selection.
Pre-applied waterproofing systems can be easily applied throughout the horizontal plain to either well compacted ground, sand or concrete blinding layer.
It is important that the system bonds directly to the poured concrete to prevent water tracking between the concrete and the membrane and to ensure it remains integral with the structure, should the adjacent ground or building be removed.
It is also important that the chosen system has self healing qualities as it will not be protected during the placement of the reinforcement or the concrete.
When applied vertically, consideration should be given to which substrate the membrane can be applied.
Some systems, such as Sodium Bentonite membranes, can be applied directly to the concrete or sheet piles prior to pouring the concrete, whereas other systems may require some form of additional permanent shuttering.
The levels of substrate/surface preparation required for pre-applied membranes should be considered as this may affect the membrane's overall performance.
For instance, removal of irregular finishes to concrete piles, stability of infill between contiguous piles and effective sealing of cleats between sheet piles.
Another important consideration is how to continue the waterproofing system up to DPC level once the pre-applied system reaches ground level.
The detailing of the pile capping beams is critical to the success of the waterproofing strategy and consideration should be given to using products from one manufacturer at this point to ensure one single point of responsibility.
The design team should accept that a basement structure will be subjected to hydrostatic water pressure at some point in its life therefore, to conform with BS8102:1990, consideration should be given to the provision of effective sub soil drainage, which can be difficult with boundary line construction.
However, the positive effect of adequate sub soil drainage cannot be under-estimated as it will significantly reduce the risk of water ingress and enhance the performance of the waterproofing strategy.
Finally, if the water table is categorised as permanently high and the long term effectiveness of sub soil drainage cannot be guaranteed or is unfeasible to install, the severity of the risk increases and it would be prudent to contact a specialist waterproofing manufacturer to assist in the design of the waterproofing strategy combining both internal and external solutions.