These Tubes Were Bent For Walking
The Angle Ring Company Limited undertook the bend forming of tubular steelwork used in the construction of the James Joyce bridge in Dublin.
The bridge, which spans the Liffey between Ellis Quay and Usher's Island, features twin pedestrianised walkways and viewing areas on each side of a central four-lane section carrying road traffic Tubes used for the two main arches of the bridge, together with other tubes of varying diameters, for handrails, car rails and the lower support rails of the bridge were all cold formed by Angle Ring
This article was originally published on Buildingtalk on 4 Sep 2008 at 8.00am (UK)
Related stories
UK first steel piled onshore wind turbines
UK's first onshore wind turbines to be supported on tubular steel piled foundations by Aarsleff from will form part of a new wind farm being built in County Durham.
TriAx geogrid prevents exhibit sinking
New site for WWII German U-boat, U-534, planned as tourist attraction on Merseyside, reinforced by installation of Tensar's innovative TriAx geogrid to prevent it sinking into the Mersey mud.
The main arch steelwork was formed on a large hydraulic press (thought to be the largest horizontal open press in the world), to produce complex multi-axis bends as specified for this uniquely designed structure.
The manipulation of three-dimensional points from CAD drawings were used to develop the bend geometry for individual tubes, with specialist tooling also used to maintain the integrity of the tube cross section and smooth form of the bends.
Cold forming was selected as the most efficient method of production, being less costly, time consuming or technically involved than induction bending.
The main arches were constructed using two thick-walled tubes of different sizes being 368mm and 177.8mm O/D with wall thicknesses of 80mm and 60mm respectively.
These were supplied by the main contractor Irishenco Construction, a Mowlem Group company, in straight lengths of approximately four or five metres.
Two or three of these were then welded together by Angle Ring to achieve suitable lengths for cold forming.
Owing to the three dimensional curvature of this unique bridge, created by international architect/engineer Dr Santiago Calatrava Valls, multi-axis bends were required in each formed length.
The two main parabolic arches of the bridge were constructed by joining the sections of thick walled tubes together with connecting fishplates to create two continuous, tilted, tied arches as the support spans for this unique steel structure.
The final welding fabrication and assembly work was undertaken at the Belfast shipyard of Harland and Wolff, to create a bridge with a span of 40 metres, having an overall width at the centre of 40 metres, reducing to 27 metres at each end.
Finished in gleaming white, the prestigious James Joyce bridge has proved to be a worthwhile addition to the many attractions of 'Dublins fair city'.