ISG win Grimsby Emergency Care Centre
project
ISG secure GBP2.1 million project with Northern Lincolnshire and Goole Hospitals NHS Foundation Trust to create a new Emergency Care Centre at the Diana, Princess of Wales Hospital in Grimsby.
Work to create the state-of-the-art new facility, which replaces the hospital's existing Accident and Emergency Department, will be carefully phased to ensure the unit remains fully operational during the construction programme The ECC concept brings purpose built, modern emergency facilities to the hospital, upgrading and extending the scope of emergency and specialist treatment currently available
This article was originally published on Buildingtalk on 15 Jan 2004 at 8.00am (UK)
Related stories
New Whitbread Partnering Contract
Totty Construction's partnering agreement with leisure giant Whitbread goes from strength to strength in 2004 with the award of a new contract to build a Travel Inn and Brewsters Restaurant
Totty Completes £33 Million Hat Trick
Totty Construction, the northern-based main contractor, has been awarded the final phase of the high profile Brewery Wharf residential development, by Barratt Leeds.
The contractor will adopt highly flexible working practices at the busy hospital, liaising closely with staff and carefully timing the works programme to minimise any potential disruption throughout the project.
Existing consultation and treatment rooms will be stripped out, the space reconfigured and a range of new treatment rooms constructed.
On completion of this phase, staff will take possession of these new facilities, with ISG then commencing work on the newly vacated areas within the remaining AandE department.
Accessibility is a key issue on site, with initial phases demanding the creation of a robust access policy to ensure the safe and effective movement of materials and operatives via a busy internal main corridor.
Mechanical and electrical services will be replaced throughout the new ECC, with specialist flooring and suspended ceilings installed.
Phase two of the project sees the creation of treatment rooms, a staff room, offices and a family room.
The final phase sees ISG create a high specification resuscitation suite, additional offices, file store and security room.
Initial enabling work will commence at the end of January, with the main construction programme starting at the end of March 2008, with completion scheduled for February 2009.
Paul Clarkson, regional construction director at ISG Totty Building, commented: "Working for emergency services, within live environments always presents a range of complex challenges for contractors, and our latest scheme at Diana, Princess of Wales Hospital is a text book example".
"Maintaining continuity of operations is fundamental for the existing AandE department and our phased programme has been carefully developed in conjunction with the hospital to ensure that we have minimal impact on the day to day operations of the facility, whilst providing the optimum construction solution.".