Flow controls help offset extensive flood problems

  • 29 May 2015

After existing drainage scheme failed to prevent extensive flooding in the area as recently as 2012/2013, Telford and Wrekin planners put a condition on the approval to provide a scheme to resolve the flooding issues.

Complex flow control chambers such as the one designed for Limekiln Lane are being used increasingly.

Consulting engineers Mouchel established an innovative solution based on Sustainable Drainage Systems (SuDS) principles. The system uses a configuration of three Hydro-Brake Optimum flow controls to optimise the existing back up storage volume and provide enhanced protection for the built up areas downstream.

Robust flood protection

The existing arrangement was that normal dry weather flow followed the stream course with an arrangement which allowed overflow into a dry swale. The overflow was then discharged into a bypass system of 1200 mm diameter pipes. However, the perched nature of the stream had resulted in long-term flooding when the banks were breached.

Mouchel were challenged to deliver a robust flood protection scheme using the maximum storage available within a specific area allocated on the site, which sits between a housing development and new school playing fields. The new drainage design also had to ensure that normal stream flows could continue downstream with no restriction in light flow conditions for ecology and amenity purposes.  

The existing drainage scheme was failing to prevent flooding through a nearby recent housing development

Neil Scott, Principal Engineer for Mouchel, discussed why Hydro-Brake Optimum was specified for the scheme: “As you get more flow at a lower head through the Hydro-Brake Optimum, less back up storage is required.  So, the discharge from the basin could be carefully controlled to make the most of the storage capacity available. 

“The maximum stored volume of 6,700 m3 was the total amount which could be accommodated within the area and the maximum combined continuation flow was 1.75 m3 per second. The maximum depth of water which could be achieved on the site is 2.2 m.”

With these parameters in mind, Mouchel decided to split the flow so that normal flow and flood flows activated separate flow controls installed in a concrete headwall structure to provide additional protection when required.

“With the help of Hydro’s technical design support, we devised a headwall arrangement with one flow control unit providing the continuation flow discharging at a maximum of 584 l/s through a 900 mm pipe, and units two and three on the other side of the shallow weir wall activated during peak events.”

The normal surface water intake is channelled through the continuation unit into the existing watercourse.  When the flow overtops the shallow weir wall, Hydro-Brake Optimum units two and three come into operation before combining and discharging into the 1200 mm pipe into a previously redundant overflow culvert, brought into more effective use as part of the scheme.

With all units set at the same level the flow is always split 33/66 as soon as the water level overtops the weir level.
 

Leave a Reply

Latest news

Crown

Crown supports flood-hit community in Warrington

Crown Decorating Centres’ Warrington branch has donated a thousand litres of Crown Trade Paint to 100 flood-hit local residents.

Posted in Articles, Building Industry News, Building Products & Structures, Case Studies, Charity work, Interiors, Paints, Paints, Coatings & Finishes, Restoration & Refurbishment, Retrofit & Renovation

Ignition

CBILS gives business a boost - Ignition

Ignition, a leading UK provider of vehicle and asset finance for SMEs, has been assisting businesses with securing loans through the Coronavirus Business Interruption Loan Scheme (CBILS).

Posted in Articles, Building Industry News, Building Products & Structures, Facility Management & Building Services, news, Plant, Equipment and Hire, Posts, Site Preparation

Crown

Hygienically Clean Paint from Crown Paints

Crown Trade’s Clean Extreme Anti Bacterial paint range offers the best of both worlds – a paint with added anti bacterial protection which will not diminish over time.

Posted in Articles, Building Industry News, Building Products & Structures, Health & Safety, Interior Design & Construction, Interiors, Paints, Coatings & Finishes, Restoration & Refurbishment, Retrofit & Renovation

GGF

Laminated Glass Ban Webinar Engages GGF Members

On Thursday 18 February, the GGF Document B Working Party held a Members-only Webinar on the GGF’s response to the Government ban of the use of Laminated Safety Glasses: Regulation 7/Statutory Instrument 1230.

Posted in Articles, Building Associations & Institutes, Building Industry Events, Building Industry News, Building Products & Structures, Building Regulations & Accreditations, Glass, Glazing, Health & Safety, Posts, Seminars, Windows